Design and develop a P & I D for Boiler and Heat Exchanger pilot plant

Procedure

Piping Diagram Configuration:

  • Configure all parameters for the piping diagram. In which you need to identify vessels and equipment to run the plant
  • Click on the "Verify Components" button
  • If all configuration parameters are correct, the "Next Level" button will be visible.
  • Click on the "Next Level" button to proceed

Instrument Diagram Configuration:

  • Follow the same steps as above to configure the instrument diagram. In this you will have identify the instruments required to run the plant
  • Click on the "Verify Instruments" button
  • If all configuration parameters are correct, the "Next Level" button will be visible
  • Click on the "Next Level" button to continue

Sequence of Activities:

  • Read the “Prior Knowledge Assessment” statements carefully
  • Enter the appropriate sequence number in the provided text box. The system will not allow you to write the duplicate numbers. Hence be careful
  • Click on the "Submit" button
  • You have three attempts to verify whether the sequence is correct or otherwise
  • Try for three times and then proceed to the Simulation section

Simulation Execution:

  • Click on the "Start" button to begin the simulation
  • The first time setting runs for 5 minutes by default
  • For other test cycles, you can choose different time durations such as 2 min, 3 min, 4 min, etc
  • The simulation will display the status and phases during execution
  • You can start the next test cycle or view the datasheet and trends according to the test cycles
  • The datasheet for each test cycle can be downloaded in PDF format by clicking on the "Download " button
  • Multiple readings are available in line format
  • Use the checkbox to view different series or hide specific series as needed
  • Click on the "Download Graph"button to save the graph

Data Monitoring & Graphs:

  • View the Datasheet and Trends according
  • The trend functionality allows you to see multiple readings in a line or trend format
  • Use the checkbox to switch between different series or hide/show specific data Download the graph using "Download Graph" button

Result Assessment:

  • Click on the "Result" button to view your performance assessment.