Measurement and Control system - Implementation for one application
Procedure
Basic Knowledge
- Answer all the questions and click on next level
Configuration
- Select height of tank , Enter "Setpoint" valve and click on submit button
- Select span of DPT and pressure transmitter /click the configuration button
Simulation
- Click on water inlet valve (V1) to fill the tank
- Observe the DPT reading
- After that click on valve V3 and observe DPT reading, PC reading and action on valves V4,V5 and V6
- LSL sensor turns red after water level reaches to low level
- Click on V1 to fill tank again
- Observe DPT, Pc readings and action on valves V4,V5 and V6
- Process is completed for one iteration.
Configuration for second iteration
- Select height of tank (select different height from first configuration for better understanding), Enter "Setpoint" valve and click on submit button
- Select span of DPT and pressure transmitter . click the configuration button
Simulation for second iteration
- Click on water inlet valve (V1) to fill the tank
- Observe the DPT reading
- After that click on valve V3 and observe DPT reading, PC reading and action on valves V4,V5 and V6
- LSL sensor turns red after water level reaches to low level
- Click on V1 to fill tank again
- Observe DPT, Pc readings and action on valves V4,V5 and V6
- Process is completed for both iterations. write down the observation of the plant in your note-book and click on "Result" button