Measurement and Control system - Implementation for one application

Procedure

Basic Knowledge

  • Answer all the questions and click on next level

Configuration

  • Select height of tank , Enter "Setpoint" valve and click on submit button
  • Select span of DPT and pressure transmitter /click the configuration button

Simulation

  • Click on water inlet valve (V1) to fill the tank
  • Observe the DPT reading
  • After that click on valve V3 and observe DPT reading, PC reading and action on valves V4,V5 and V6
  • LSL sensor turns red after water level reaches to low level
  • Click on V1 to fill tank again
  • Observe DPT, Pc readings and action on valves V4,V5 and V6
  • Process is completed for one iteration.

Configuration for second iteration

  • Select height of tank (select different height from first configuration for better understanding), Enter "Setpoint" valve and click on submit button
  • Select span of DPT and pressure transmitter . click the configuration button

Simulation for second iteration

  • Click on water inlet valve (V1) to fill the tank
  • Observe the DPT reading
  • After that click on valve V3 and observe DPT reading, PC reading and action on valves V4,V5 and V6
  • LSL sensor turns red after water level reaches to low level
  • Click on V1 to fill tank again
  • Observe DPT, Pc readings and action on valves V4,V5 and V6
  • Process is completed for both iterations. write down the observation of the plant in your note-book and click on "Result" button