Soundness of Cement
Step 1: Weighing of Cement
• Click on the weighing plate to place it on the weighing machine.

• Click on tare to set the reading to zero.

• Using a spatula, accurately weigh 200 g of cement.

• Click on Next to proceed.
Step 2: Weighing of Water
• Click on the beaker to place it on the weighing machine.

• Click on the Tare button to measure its weight.

• Click on the measuring cylinder and weigh water equal to 0.78P × weight of cement.

• After measuring the required quantity of water, click on Next.
Step 3: Preparation of Cement Paste
• Click on the beaker to add water to the cement.

• Click on the spatula and mix thoroughly to obtain a uniform and homogeneous paste.

• After proper mixing, click on Next.
Step 4: Filling the Le Chatelier’s Mould
• Click on the brush and apply a thin layer of oil to the inner surface of the mould.

• Click on the glass plate and place the mould apparatus on it.

• Using a spatula, fill the mould completely with the prepared cement paste.

• Click on the apparatus to spread the paste evenly.

• Place another glass plate on top of the mould.

• Click on the weight and place it over the glass plate to apply uniform pressure.

• Click on Next.
Step 5: Immersion in Water
• Click on the Le Chatelier’s apparatus to immerse the complete assembly in the water tank.

• After 24 hours, click on the apparatus to remove it from the water.

• Click on the scale to measure the distance between the two indicator points of the mould.

• Click on Next.
Step 6: Boiling and Final Measurement
• Click on the setup to place the mould assembly into boiling water.

• After boiling, click on the scale and measure the distance between the two indicator points again.

Finally, click on Post Test to evaluate your understanding of the experiment.