COEP TECHNOLOGICAL UNIVERSITY PUNE

COMMISSIONING

You are appointed as 'commissioning Engineer' by your firm and assigned you a job of commissioning of a Boiler and Heat Exchanger Plant. List the documents you will collect for the starting of commissioning activity.
  1. Fully automatic plant with PLC control and SCADA interface
  2. A steam of 30 Kg/Hr at 3.5 Kg/cm2, and 135°C
  3. The steam will be used to produce hot water up to 80°C, with 800 LPH flow
  4. The condensate will be used as feed water to improve efficiency
  5. Three level interlocks are used to protect the plant
  6. The plant should generate the data so as to monitor vital health parameters of the plant