You are appointed as 'commissioning Engineer' by your firm and assigned you a job of
commissioning of a Boiler and Heat Exchanger Plant. List the documents you will collect
for the starting of commissioning activity.
- Fully automatic plant with PLC control and SCADA interface
- A steam of 30 Kg/Hr at 3.5 Kg/cm2, and 135°C
- The steam will be used to produce hot water up to 80°C, with 800 LPH flow
- The condensate will be used as feed water to improve efficiency
- Three level interlocks are used to protect the plant
- The plant should generate the data so as to monitor vital health parameters of the plant